A real estate developer in Boston, Massachusetts, was constructing a mixed-use residential tower with 135 units and 10,000 sq ft of retail space. Construction start was delayed, and the team needed to make up lost time while maintaining quality and safety .
The original plan used traditional plywood decking and timber beams, which presented several problems:
Slow cycle times — each floor slab took 8–10 days to complete
Heavy components — required constant crane use for material handling
Labor intensive — needed skilled carpenters for assembly and stripping
High re-shoring requirements — entire formwork had to stay in place until concrete reached full strength
The contractor needed a lightweight, high-efficiency slab formwork system that could accelerate construction while reducing labor and crane dependency.
The team switched to the Alu Skydeck aluminum panel slab formwork system — specifically the PERI SKYDECK system used extensively on projects worldwide .
Key technical specifications:
| Feature | Specification |
| Panel material | Aluminum 6061-T6 alloy |
| Panel weight | 15.5–16.2 kg per 750×1500mm panel |
| Prop density | Only 0.29 props per m² |
| Max slab thickness | Up to 109 cm (with appropriate beam configuration) |
| Formlining | 9 mm FinPly / phenolic plywood |
Core technology — Drophead system:
The Skydeck system features a patented drophead mechanism that allows early striking of panels and beams while props remain in place. After concrete pouring (typically 24–48 hours), a single hammer blow lowers the drophead by 60 mm, allowing panels and main beams to be stripped and moved to the next level while the props continue supporting the curing slab .
On-site implementation:
20,000 sq ft of Skydeck formwork deployed for first-level structural slab and second-level post-tension slab
Systematic assembly sequence required minimal training
Lightweight components allowed hand-carrying by two workers, eliminating crane dependency
| Metric | Traditional Timber/Aluminum Comparison | Alu Skydeck System | Improvement |
| Floor cycle time | 8–10 days | 5–6 days | 30–40% faster |
| Crane dependency | High (requires crane for panel placement) | None (panels under 16 kg, hand-carried) | Crane time freed |
| Labor skill required | Skilled carpenters | Semi-skilled workers | Lower labor cost |
| Prop requirement per m² | 0.8–1.0 props | 0.29 props | 65% fewer props |
| Reuse cycles | 5–10 uses | 80–120 uses | Long-term cost saving |
Schedule impact: The developer completed the post-tension slab on schedule despite the delayed start. Production was described as having “increased exponentially” after switching to Skydeck .
For multi-story projects with repetitive floor layouts, the Alu Skydeck system delivers significant advantages :
Faster construction cycle
Early striking with drophead — panels reused on next level while props remain as re-shoring
Systematic assembly — panels lock into place without swaying, no complex measuring required
Lower labor costs
Single carpenter + two general operatives can manage the system
Minimal training required — unskilled workers learn quickly
Reduced equipment inventory
Only 0.29 props per m² (vs. 0.8–1.0 for traditional systems)
Fewer props means less material to store and transport
Safety advantages
Integrated edge protection solutions available
Stable platform at all times — no working at height during panel placement
Proven worldwide
Used on projects from London’s Grosvenor Waterside to Milwaukee’s 36-story University Club Tower
A peer-reviewed study published in the Journal of Sustainable Architecture and Civil Engineering evaluated three formwork systems for high-rise slab construction using the TOPSIS method. The evaluation criteria included labor costs, assembly complexity, rental price, and demoulding time. The SKYDECK aluminum panel system ranked as the optimal choice for multi-story concrete slab construction .
Switching to the Alu Skydeck Formwork System enabled this Boston developer to recover from a delayed start, reduce crane dependency, and accelerate floor cycles by 30%. The combination of lightweight aluminum components, drophead early-strike technology, and minimal prop requirements delivered measurable time and cost savings.
Ready to accelerate your next high-rise project?
![]()