A university apartment building project (Dongguan, China) required fast, high-quality construction across 20+ repetitive floors. Using traditional timber formwork, the team faced:
Long floor cycles — timber required extensive on-site fabrication
High labor costs — skilled carpenters needed for cutting and assembly
Quality inconsistency — timber deformation led to uneven concrete surfaces
With 80 workers on-site simultaneously, they needed a system that could accelerate the schedule while reducing labor dependency .
The team switched to a 150 aluminum framework plywood system, combining aluminum frames with replaceable plywood faces .
Key advantages on site:
Lighter than steel — faster handling, less crane dependency
Pre-engineered panels — eliminated on-site cutting and fabrication
Smooth concrete finish — achieved blank concrete façade standard, eliminating plastering
| Metric | Traditional Timber | Aluminum Frame | Saving |
| Floor cycle time | 13 days | 7 days | 6 days saved per floor |
| Main structure workers | ~70 | 48 | 22 fewer workers |
| Labor cost per floor | Baseline | ¥105,600 less | 13.5% reduction |
Source: Construction log data, Dongguan University Apartment Project
Outcome: Each floor completed in 7 days vs. 13 days with timber. The system delivered consistent quality across all repetitive floors with significant labor savings.
For multi-story residential and apartment projects:
30–40% lighter than solid aluminum — easier handling
Replaceable plywood face — frame lasts 150+ uses
Blank concrete finish — no plastering required